A cedar-shingled gabled window bay with charcoal frames, a basalt foundation, and autumn oakleaf hydrangea beside sword ferns.

Every Plan to Grow Lake Oswego's Library Has Run Into the Same Lot. This One Starts by Leaving It.

November 5, 2026

In August 1983, Lake Oswego opened its new library at Fourth and D, and Oregon Poet Laureate William Stafford read a poem at the celebration. One line from it is still quoted on the library's history page: "the nudge of a book and all of history crystallizes for a dazzled reader again and again."

The same page records something less festive about that day. The 27,000-square-foot building that opened was 23% smaller than what voters had approved in 1974. Construction didn't start until 1982 because of disagreements over the site and the building plans. Within a few years, concerns about space, parking and long-term capacity had started.

That history explains the city's newest step. On Tuesday, Oct. 20, the City Council voted to hire Shiels Obletz Johnsen as owner's representative for a new library, the Lake Oswego Review reported. The firm's tasks include site selection, design, acquisition and financial planning. The first item on that list is the one this town has never solved. For four decades, the library's problem has been its ground more than its walls.

Six decades on one corner

The library has been on the same corner since before the current building existed. A parcel donated by John and Elizabeth Gray, together with a bond issue, paid for a 7,400-square-foot library at Fourth and D Streets, dedicated in May 1962. Every effort to grow it since then has hit the same limit:

  • 1974. Voters pass a bond to expand. Disagreements over the site and plans delay construction until 1982.
  • 1983. The current building opens, smaller than voters approved.
  • 1988, 1992, 1996. The Library Growth Task Force, a branch site committee and a building program report each recommend a larger facility.
  • 2006. Another study recommends a larger main library or a branch.
  • 2012. The city proposes a 60,000-square-foot library at First Street and B Avenue as part of the downtown North Anchor redevelopment, paid for with a $14 million bond plus urban renewal funds. The bond measure fails in November.
  • 2024. The city looks at a combined community center and library at Lake Grove Elementary on the west side. Your Oregon News reported that the idea ended when the school district decided to rebuild the school.

Location runs through every one of these. Site disputes held up the 1974 plan for eight years, and the 2012 proposal was tied to a single downtown block and ended when its bond failed. In 2024, the west-side option disappeared once the school property it relied on was no longer available.

Library Director Melissa Kelly spelled out the current version of the problem at the Oct. 20 meeting. "The library is in need of replacement in the next few years because the existing building has reached the limit of its useful life despite care and maintenance and its footprint can't be expanded to meet community needs at its existing site," she said, according to the Review.

The city's own documents describe the building's condition: seismic, water intrusion, building system and accessibility problems that keep getting worse. The city's August 2026 planning FAQ estimates repairs at $10 million, and those repairs would still leave the site's core limits in place. Meanwhile, the same FAQ says the building serves more than 41,000 residents, holds a collection of over 300,000 items and handles about 800,000 checkouts a year.

What the city is looking for this time

The council's library goal, adopted in March 2026, is to "develop a strategy for an expanded and modern library facility, prioritizing the West side of town and urban renewal funding options, allowing it to serve as an all-ages and all-activities community center."

To find that land, the city issued a request for proposals for a real estate broker on Oct. 19. The document lists the site criteria the council has adopted:

  1. Adequately sized. A pre-building program study found the project needs a site of 2.5 to 3.5 acres. Sites of 2 acres or more will also be considered, so a good option just under 2.5 acres isn't missed.
  2. Equitably and accessibly located. More central to the city's population, in a visible spot near an arterial road, and reachable on foot, by bike, by car and by transit.
  3. Financially feasible. Inside, or able to be added to, an urban renewal district with the capacity to help fund the project.
  4. Appropriately zoned. A site that can be zoned for a public library.

The RFP also names an area. "The Lake Grove Urban Renewal District is both centrally located and has the capacity to help fund the project," it says. The city treats Lake Grove as a funding and location priority. Its FAQ says the actual location will be decided through analysis against these criteria and through public input.

The RFP also says why the city wants that much land. A larger site is seen as the only workable way to add large public meeting rooms, bigger children's and teen areas and a makerspace, which the 1983 building and its lot can't fit. In July, the Review reported that Kelly pictured a two-story building that could be more than twice the size of the current one.

The calendar between now and a site

The broker search runs on a short schedule. Proposals are due this Friday. Here are the dates from the RFP and the council's timeline:

Date Step
Nov. 6, 2026 Broker proposals due, 4:30 p.m.
Nov. 20, 2026 Broker interviews
Nov. 30, 2026 Notice of intent to award
Dec. 16, 2026 Anticipated broker contract start
March 2027 Council target for preliminary site options
Q3 2027 Council target for two viable acquisition options
June 30, 2028 Broker project completion date

The city says it may change this schedule. The July Review article described a longer projection, with decisions continuing through 2028 and design and construction possibly falling between 2029 and 2031. The owner's representative contract is capped at less than $299,925, and the firm is paid by the hour.

Two task forces, one for each address

The city has set up two groups because leaving the old lot raises its own question.

The Future Library Task Force will shape the building and site program, rank possible sites and recommend a preferred site and a backup to the council. It will have up to 20 community members. Seats are set aside for youth, parents, older adults, people with disabilities, business, schools, Friends of the Library, city boards and at-large residents. The city expects it to meet about eight times, no more than once a month, starting in December 2026 and continuing through 2027. That puts its first meetings close to the broker's start date.

The Library Site Reuse Task Force is focused on Fourth Street. It will develop and evaluate options for the current library property after the library moves, and then make a final recommendation. Its up to 20 seats include representatives from the First Addition Forest Hills, Evergreen and Old Town neighborhood associations, downtown businesses, city boards, youth, the Adult Community Center user group and at-large residents. It is expected to meet about six times in person between August 2026 and April 2027. Members of the public can email comments at least 48 hours before a meeting.

That reuse group is the more immediate one for anyone living within walking distance of Fourth and D. Its recommendation is due well before any new building opens, and it covers a downtown parcel the library has held since 1962.

The building still has a full winter

Planning a replacement hasn't shut down the current library. On Tuesday, Dec. 1, from 5:30 to 6:30 p.m., the library at 706 Fourth Street hosts a Czech Christmas program of music and stories with Mark and Helena Greathouse, part of its First Tuesday Music and Memories series. It will also be livestreamed for anyone who can't come in person.

For more on how the town's public spaces fit together, our Lake Oswego neighborhood guide maps the city by area, and our summer piece on Lake Oswego's rotating park concerts shows how much of civic life already moves between neighborhoods.

If you live near First Addition or Lake Grove and want to talk through what a library decision could mean for your corner of town, the team at Monaghan Real Estate Group is following this project closely and would be glad to compare notes over coffee. Let's Connect.

Work with Us

We truly would like to see how we can help you attain your real estate goals. It is our passion to help people whether it’s meeting an immediate need or helping create a long-term plan. We look forward to meeting to discuss your goals to create a customized plan for you. Please contact us today so we can be in touch straight away.